Case 2302282/2021 · Employment Tribunal
Pamela Alty v Links Waste Management Ltd. t/a JM Waste Management — 2022
- Case reference
- 2302282/2021
- Decision date
- 15 December 2022
- Jurisdiction
- England & Wales
- Judge
- Employment Judge Hart Representation
Parties
2 namedClaimant
Pamela Alty
Key findings
Tribunal's reasoningThe tribunal found that the claimant became an employee of Links Waste Management Ltd from 29 April 2019 under an oral agreement made on 26 April 2019 for fixed hours and pay, despite the absence of a written contract and the fact that payroll only began on 10 June 2019. Applying the Ready Mixed Concrete approach, it held that the reality of the relationship from 29 April 2019 was employer and employee. It also rejected the illegality point about the cash expenses arrangement, finding the parties had acted in good faith and that Patel v Mirza would not bar relief.
On continuity, the tribunal held that the move between Links Waste Management Ltd and The Work Cafe Ltd did not break service because the companies were associated within section 218(6) ERA 1996. Links controlled The Work Cafe directly through shareholding and indirectly through Mr Stone's control of both companies, and in each move the claimant started with the successor employer on the next working day. That meant she had the continuous service needed for unfair dismissal and redundancy pay purposes.
The tribunal found that the dismissal on 1 June 2021 was unfair. Although the dismissal letter referred to a restructure, the tribunal accepted Mr Stone's evidence that this was not the real reason. The principal reason was that he considered the claimant no longer to be an 'A' player after he had been told she was looking for other work and had asked for a reference. The tribunal rejected the suggestion that she was attending interviews in work time, held that looking for other work was not misconduct, and said that even if the matter were treated as SOSR or a breakdown in relations, the dismissal was still unfair because there had been no warning, no proper meeting, no chance to respond or improve, no consideration of alternatives and no appeal.
For remedy, the tribunal awarded a basic award of £1,174.50 and a compensatory award of £3,809.67 for unfair dismissal. It found that the claimant took reasonable steps to mitigate her loss, but concluded that there was a 50% chance she would have left later when she obtained the Castle Accommodation role, so later losses were reduced on a just and equitable basis. The tribunal also applied a 10% ACAS uplift because of failures in the disciplinary and grievance process, a section 38 Employment Act 2002 uplift for failure to provide written particulars, and then reduced the unfair dismissal award by 10% for contributory fault.
The notice pay claim succeeded because the claimant should have had two weeks' notice but only received one week, so the tribunal ordered £385.31 net after the ACAS uplift. The holiday pay claim succeeded because the tribunal found that 20 days from the 2020-2021 leave year could be carried over due to coronavirus, then deducted 1.4 days already taken and applied the uplift, resulting in £1,433.43 net. The written statement claim also succeeded and was valued at two weeks' pay, £700.56 net. The redundancy pay claim was dismissed, and the pension-contribution and May 2021 unlawful-deduction complaints were withdrawn and dismissed upon withdrawal. The recorded awards sum to £7,503.47.
Claims and outcomes
7 findings recordedThis case has mixed outcomes under at least one legal claim type. A tribunal can uphold some allegations and dismiss others under the same legal head, so rows below may represent separate issues or allegation groups from the judgment.
| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Unfair dismissal | The tribunal found the dismissal on 1 June 2021 was unfair. It rejected redundancy/restructure as the real reason and found the principal reason was that Mr Stone considered the claimant no longer to be an 'A' player after she was looking for other work and had sought a reference; no fair warning, meeting, appeal or alternative was provided. | Upheld | — | £4,984 |
| Breach of contract | Notice pay claim. The tribunal found the claimant was entitled to two weeks' notice but had only been paid one week's pay, so a further week's pay of £350.28 net plus a 10% ACAS uplift was ordered. | Upheld | — | £385 |
| Holiday pay | Holiday pay claim under the Working Time Regulations. The tribunal found it was not reasonably practicable for the claimant to take leave in the 2020-2021 leave year because of coronavirus, so 20 days carried over; after deducting 1.4 days taken in the 2021-2022 leave year and adding the 10% ACAS uplift, £1,433.43 net was ordered. | Upheld | — | £1,433 |
| Other | Failure to provide a written statement of employment particulars. The tribunal found no written statement was provided and awarded two weeks' pay under section 38 Employment Act 2002, rather than the four weeks sought. | Upheld | — | £701 |
| Redundancy |
Remedy
Monetary award- Total award
- £7,503
- across all upheld claims
- Basic award
- £1,175
- statutory, unfair dismissal
- Compensatory award
- £3,810
- compensatory remedy recorded
Legal tests applied
9 references- Ready Mixed Concrete multi-factor test
- section 230 ERA 1996 worker/employee distinction
- s.218(6) ERA 1996 associated employer continuity
- s.98(4) ERA 1996 range of reasonable responses
- Polkey / Contract Bottling 'what would have happened'
- contributory fault under ss.122(2) and 123(6) ERA 1996
- ACAS Code uplift under s.207A TULRCA 1992
- s.38 Employment Act 2002
- Patel v Mirza
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.