Case 2305522/2021 · Employment Tribunal
Mr Henryk Rezler v TSP Contracting Limited — 2023
- Case reference
- 2305522/2021
- Decision date
- 20 January 2023
- Jurisdiction
- England & Wales
- Judge
- Employment Judge Hart REPRESENTATION
Parties
2 namedClaimant
Mr Henryk Rezler
Respondent
Key findings
Tribunal's reasoningMr Henryk Rezler worked for TSP Contracting Limited as a tiler from 18 September 2018 to 23 July 2021. Although both parties treated him as self-employed, the tribunal found that he worked solely for the respondent, at fixed hours, personally, and under Mr Piotrowski's direction as to where, when and how the work was done. He had no substitution right, carried no real financial risk, and was paid a daily rate. On that evidence the tribunal found that he was a worker under s.230(3)(b) ERA 1996 and also an employee applying the Ready Mixed Concrete multi-factor approach, with the reality-of-the-relationship principle reflected in Autoclenz and Uber.
On wages, the respondent accepted that it had not paid the claimant for 19 to 23 July 2021. The tribunal found that there was no written contract, no prior written notification, no written consent and no statutory basis authorising the deduction, so the non-payment was an unlawful deduction of wages. The tribunal also found a breach of contract on the same facts, but made no separate award because the contractual claim duplicated the £700 net awarded for unlawful deduction of wages.
On holiday pay, the tribunal held that the claimant was entitled to 5.6 weeks' leave as a worker. For the final leave year, running from 18 September 2020 to 23 July 2021, it found that 24 days had accrued by termination and awarded £3,360 net at £140 per day. For the previous two leave years, it applied the King v Sash Window Workshop principle because there was no evidence that the claimant had been informed of or encouraged to take paid leave, and awarded 40 days at £140 per day, namely £5,600 net. The tribunal therefore accepted that the respondent's treatment of the claimant as self-employed did not defeat his accrued holiday rights.
The respondent had never provided a written statement of particulars. Because the claimant was found to be an employee and had succeeded in the wage and holiday pay claims, s.38 Employment Act 2002 required an award. The tribunal rejected the claimant's request for four weeks' pay as not just and equitable, noting that the failure was based on a mistaken belief that he was self-employed and that the respondent was a very small employer. It awarded two weeks' pay of £1,750 gross. The total awards were £11,410 made up of £700 net, £3,360 net, £5,600 net and £1,750 gross.
Claims and outcomes
5 findings recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Breach of contract | Breach of contract was found in relation to the same unpaid week of wages, but no additional award was made because the sum duplicated the unlawful deduction award. | Upheld | — | — |
| Unlawful deduction from wages | Non-payment of wages for 19 to 23 July 2021; respondent accepted £700 net (£875 gross) was unpaid. Tribunal found no authorised deduction and no s.14 ERA 1996 exemption applied. | Upheld | — | £700 |
| Holiday pay | Accrued holiday pay on termination. Tribunal found 24 days had accrued in the final leave year (18 September 2020 to 23 July 2021) at £140 net per day. | Upheld | — | £3,360 |
| Holiday pay | Holiday pay for the previous two holiday years. Tribunal applied the King v Sash Window Workshop principle and awarded 40 days at £140 net per day because the claimant had not been informed of or encouraged to take paid leave; no reg 13A carry-over agreement existed. | Upheld | — | £5,600 |
| Other | Failure to provide a written statement of particulars. Tribunal awarded two weeks' pay under s.38 Employment Act 2002 and declined four weeks' pay as not just and equitable. | Upheld | — | £1,750 |
Remedy
Monetary award- Total award
- £11,410
- across all upheld claims
Legal tests applied
8 references- s.230 ERA 1996 worker/employee definition
- Ready Mixed Concrete multi-factor approach
- Autoclenz Ltd v Belcher reality of relationship principle
- Uber BV & Others v Aslam & Others reality of relationship principle
- s.13 ERA 1996 authorised deduction test
- King v Sash Window Workshop leave carry-over principle
- Smith v Pimlico Plumbers Ltd leave carry-over principle
- s.38 Employment Act 2002 just and equitable assessment
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.