Case 2501355/2024 · Employment Tribunal
Mr. N. Rutter v J R Dynamics Limited — 2024
- Case reference
- 2501355/2024
- Decision date
- 26 August 2024
- Jurisdiction
- England & Wales
- Judge
- Employment Judge T.R. Smith
Parties
2 namedClaimant
Mr. N. Rutter
Respondent
Key findings
Tribunal's reasoningMr N. Rutter brought a single complaint of breach of contract arising from non-payment of part of his notice period between 16 April and 28 April 2024. He later confirmed that he was not pursuing any complaint about pension contributions. The parties agreed that, if breach were established, damages would be £1,833.43.
The tribunal found that the claimant started work on 1 March 2024 as an embedded system developer on a three-month probationary contract, with four weeks' notice on termination. The respondent decided on 28 March 2024 to end the employment within the probationary period. The claimant chose to work out his notice. The parties agreed that he would work from home in April using company equipment, but the tribunal found that this was expressly on the basis that he would perform the allocated work efficiently. The tribunal accepted that there were communication difficulties and that the claimant said these were caused by Google mail and equipment issues, but it did not need to decide where fault lay.
The tribunal held that the claimant had no contractual right to insist on working from home because his place of work under the contract was the respondent's premises and there had been no contractual variation supported by consideration. It referred to Buckland -v- Bournemouth University Higher Education Corporation [2010] IRLR 445 and Tenon FM Ltd -v- Cawley 2018 EWHC 1972. Even if there had been an oral variation, the tribunal found it was conditional on productive work, and that condition was not met. When the claimant refused to return to the respondent's premises, the tribunal found that he breached a fundamental term of the contract. The respondent was therefore entitled to treat the contract as terminated and to stop paying the remaining notice pay. The breach of contract complaint was dismissed.
Claims and outcomes
1 finding recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Breach of contract | The parties agreed damages of £1,833.43 if breach were proved, but the tribunal dismissed the claim so no contractual damages were awarded. | Dismissed | — | — |
Legal tests applied
2 references- Buckland -v- Bournemouth University Higher Education Corporation [2010] IRLR 445
- Tenon FM Ltd -v- Cawley 2018 EWHC 1972
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.