Case 3302401/2020 · Employment Tribunal
Dr. M Abbasi v University of Surrey FINAL HEARING — 2024
- Case reference
- 3302401/2020
- Decision date
- 29 January 2024
- Jurisdiction
- England & Wales
- Judge
- Employment Judge Boyes
- Venue
- Bury St Edmunds
- Panel members
- Mr C. Davie, Ms C. Smith
Parties
2 namedClaimant
Dr. M Abbasi
Respondent
Key findings
Tribunal's reasoningThe tribunal rejected the breach of contract claim. It found that the Enhanced Voluntary Severance scheme was expressly described as non-contractual in the scheme documents and FAQs, including the February 2019 FAQ stating that EVS was not a contractual right. On that basis, no contractual entitlement arose from the scheme itself, from later FAQ changes, from Professor Richter’s conversation with the claimant on 28 March 2019, or from Professor Miller’s letter of the same date. The tribunal accepted that the claimant had been given incorrect information on 28 March 2019, but found the error was corrected later that day and that the letter was intended to leave open the possibility of an EVS application rather than to approve one.
The tribunal upheld the claim under the Fixed-Term Employees (Prevention of Less Favourable Treatment) Regulations 2002. Although the respondent had described the claimant’s role as having permanent status from 1 August 2016, the tribunal found that, in reality, he continued to be treated as a fixed-term employee because he was repeatedly told that his post would end on specified dates. It accepted the claimant was treated as a fixed-term employee at the material time and found PR was a comparable permanent employee. It also found that the claimant was referred to as a fixed-term employee in the EVS spreadsheet and related email correspondence.
On time limit, the tribunal held that the detriment did not crystallise on 28 March 2019, because Professor Miller’s letter created the impression that EVS might still be available. It found the claimant became aware definitively that he would not receive an EVS payment only on 2 September 2019, so the claim was in time; alternatively, it would have been just and equitable to extend time. On justification, the tribunal accepted the respondent’s general reasons for introducing EVS, including cost savings and reducing compulsory redundancies, but held that those reasons did not justify excluding this claimant on the facts. It found the respondent had acted on an incorrect understanding of the funding position for the Designscapes project, accepted evidence that the project continued beyond the claimant’s departure, and noted that the claimant was involved in other work and projects as well.
The tribunal awarded the claimant £17,769.50, being the amount he would have received under EVS if his application had been accepted. It rejected the respondent’s argument for any reduction based on later pay received up to 16 January 2020 and said there was no basis in regulation 7 for such a deduction. A separate case management order was to be issued on interest.
Claims and outcomes
2 findings recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Breach of contract | The tribunal held that the EVS scheme was non-contractual and that neither the February/May 2019 scheme documents, Professor Richter’s conversation on 28 March 2019, Professor Miller’s letter the same day, nor the 10 April 2019 staff email created a contractual entitlement to payment. | Dismissed | — | — |
| Fixed-term employee regulations | The tribunal found that the claimant was treated in practice as a fixed-term employee, that PR was a comparable permanent employee, and that exclusion from EVS because the claimant had an end date amounted to less favourable treatment and a detriment that was not objectively justified. | Upheld | — | £17,770 |
Remedy
Monetary award- Total award
- £17,770
- across all upheld claims
Legal tests applied
8 references- Investors Compensation Scheme Ltd v West Bromwich Building Society (No. 1)
- Harlow v Artemis International Corporation Ltd
- Cosmos Holidays plc v Dhanjal Investments Ltd
- Adams and ors v British Airways plc
- Coutts and Co plc and anor v Cure and anor
- Del Cerro Alonso v Osakidetza (Servicio Vasco de Salud)
- Montero Mateos v Agencia Madrilena de Atencion Social
- Grupo Norte Facility SA v Moreira Gomez
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.