Case 3308824/2022 · Employment Tribunal
Mr C Burrows v The Cambridge Building Society — 2023
- Case reference
- 3308824/2022
- Decision date
- 27 February 2023
- Jurisdiction
- England & Wales
- Judge
- Employment Judge Varnam Representation
Parties
2 namedClaimant
Mr C Burrows
Respondent
Key findings
Tribunal's reasoningMr Burrows was employed from 5 July 2021 as Head of Customer Strategy on a fixed-term contract with a six-month probationary period. The tribunal held that the contract allowed one week's notice during probation and three months' notice afterwards, and that the Respondent's letter of 17 December 2021 validly gave notice to terminate the employment on 28 January 2022. The oral conversation on 3 December 2021 was not sufficient notice, but the written letter was clear and specified the end date.
The tribunal then held that the probationary period ended on 4 January 2022, so when the Respondent emailed the dismissal letter on 5 January 2022 it was no longer entitled to rely on the one-week probationary notice provision. The 5 January dismissal itself was lawful under clause 16.1, which allowed payment in lieu of notice, but the amount of that payment had to reflect the remaining period to 28 January 2022 rather than just one week's pay. The Respondent therefore breached the contract by underpaying the PILON.
The tribunal rejected the Claimant's argument that clause 3.1 only permitted one week's notice where there were genuine performance or conduct concerns, and rejected the Respondent's argument that the probationary period continued until written confirmation under clause 3.3. It also rejected recovery of employer pension contributions and other benefits because clause 16.1 permitted a PILON of basic salary only. The ACAS uplift argument failed because the dismissal was not for conduct reasons. Damages were assessed at gross basic pay of £2,893.15 for 13 to 28 January 2022.
Claims and outcomes
1 finding recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Breach of contract | The tribunal held that the respondent breached the contract by paying only one week's PILON on 5 January 2022, after valid notice had already been given on 17 December 2021 to terminate on 28 January 2022. Damages were limited to basic salary; claims for pension contributions and other benefits were rejected. | Upheld | — | £2,893 |
Remedy
Monetary award- Total award
- £2,893
- across all upheld claims
Legal tests applied
4 references- objective contractual interpretation (Investors Compensation Scheme v West Bromwich Building Society)
- contract read as a whole; specific provision overrides general provision (Lewison; Apache North Sea Ltd v Ineos FPS Ltd)
- clear and unambiguous notice of dismissal with an ascertainable end date (Morton Sundour Fabrics Limited v Shaw)
- ACAS Code applies to conduct dismissals only (Holmes v Qinetiq Ltd)
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.