Case 6017656/2024 · Employment Tribunal
D Dejevs v Jenkins Stone Company Ltd — 2025
- Case reference
- 6017656/2024
- Decision date
- 8 July 2025
- Jurisdiction
- England & Wales
- Judge
- Employment Judge Dawson
Parties
2 namedClaimant
D Dejevs
Respondent
Key findings
Tribunal's reasoningThe claim was presented in the South West Employment Tribunal on 6 November 2024. The respondent failed to present a valid response on time, and the Employment Judge determined under rule 22 of the Rules of Procedure that a determination of the claim could properly be made.
The tribunal found that the respondent had made unauthorised deductions from the claimant's wages and ordered the respondent to pay £4330.00 gross. The tribunal also found that the claimant was dismissed by reason of redundancy and was entitled to a redundancy payment of £2650.00.
The respondent was ordered to pay the claimant £6980.00 in total.
Claims and outcomes
2 findings recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Unlawful deduction from wages | Tribunal found the respondent made unauthorised deductions from the claimant's wages and ordered payment of £4330.00 gross. | Upheld | — | £4,330 |
| Redundancy | Tribunal found the claimant was dismissed by reason of redundancy and is entitled to a redundancy payment of £2650.00. | Upheld | — | £2,650 |
Remedy
Monetary award- Total award
- £6,980
- across all upheld claims
Legal tests applied
1 reference- rule 22 of the Rules of Procedure
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.