Case 3200379/2023 · Employment Tribunal
Mr J Nielssen v Red Pill Productions Limited — 2023
- Case reference
- 3200379/2023
- Decision date
- 25 June 2023
- Jurisdiction
- England & Wales
- Judge
- Employment Judge S Shore Representation
Parties
2 namedClaimant
Mr J Nielssen
Respondent
Key findings
Tribunal's reasoningThis was an open preliminary hearing on limitation only. The tribunal found that Mr Nielssen was employed by Red Pill Productions Limited as an Account Director from 31 May 2022 and that the dismissal decision was communicated at the meeting on 20 September 2022. The claimant argued that his employment ended later because of probation issues, garden leave and payment in lieu of notice, but the tribunal held that the effective date of termination for limitation purposes was 20 September 2022 and distinguished Geys v Société Générale London Branch. It also found there was no express contractual right to extend probation, although the claimant had acquiesced in an extension to 30 September 2022.
On that basis, the discrimination complaints were out of time. The tribunal treated the last act relied on as 20 September 2022 and held that ACAS early conciliation, which began on 4 January 2023, came too late. It considered the claimant's allegations of direct disability discrimination, harassment, failure to make reasonable adjustments and victimisation, but refused to extend time on the just and equitable basis under section 123 Equality Act 2010. In doing so it relied on Robertson v Bexley Community Centre TA Leisure Link, British Coal Board v Keeble, Adedeji v University Hospital Birmingham NHS Foundation Trust and related authorities, and found that the claimant had not shown good reason for the delay and had produced no medical evidence showing that illness prevented an in-time claim.
The non-discrimination claims were also dismissed as out of time. The tribunal held that the claims for written reasons for dismissal under section 93(3) Employment Rights Act 1996, holiday pay under Regulation 30 of the Working Time Regulations 1998, breach of contract under Article 7 of the Employment Tribunals Extension of Jurisdiction (England and Wales) Order 1994, and unauthorised deduction from wages were all presented too late. Applying Palmer, Dedman and Schultz, it found it was reasonably practicable for the claimant to bring those claims in time because he knew his rights, had calculated limitation dates himself, and had simply misapplied the law on the effective date of termination and the relevant time limits. No remedy was awarded because all claims were dismissed.
Claims and outcomes
8 findings recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Disability discrimination | Direct disability discrimination, including the allegation that the dismissal on 20 September 2022 was because of disability, was dismissed as out of time. | Dismissed | Disability | — |
| Harassment | Harassment related to disability, including allegations connected with diabetes, ADHD, depression and anxiety, was dismissed as out of time. | Dismissed | Disability | — |
| Disability discrimination | The complaint of failure to make reasonable adjustments was dismissed as out of time; the tribunal treated any such complaint as arising no later than 20 September 2022. | Dismissed | Disability | — |
| Victimisation | The victimisation complaint, based on the claimant saying he raised disability issues and was then dismissed shortly afterwards, was dismissed as out of time. | Dismissed | Disability | — |
| Unlawful deduction from wages | The unauthorised deduction from wages complaint, including the claimant's notice-pay complaints as the tribunal analysed them, was dismissed as out of time. | Dismissed | — | — |
| Breach of contract | The breach of contract claim, which the tribunal understood to cover expenses and notice pay, was dismissed as out of time. |
Legal tests applied
14 references- section 123 Equality Act 2010
- just and equitable extension
- Robertson v Bexley Community Centre TA Leisure Link
- British Coal Board v Keeble & Others
- Adedeji v University Hospital Birmingham NHS Foundation Trust
- section 93(3) Employment Rights Act 1996
- Regulation 30 Working Time Regulations 1998
- Article 7 Employment Tribunals Extension of Jurisdiction (England and Wales) Order 1994
- reasonably practicable test
- Palmer v Southend on Sea Borough Council
- Dedman v British Building and Engineering Appliances Ltd
- Schultz v Esso Petroleum Co
- Meaker v Cyxtera Technology UK Limited
- Geys v Société Générale London Branch
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.