Case 8000863/2024 · Employment Tribunal
EMPLOYMENT TRIBUNALS (SCOTLAND) Case No: 8000863/2024 Miss C Potter v Edinburgh Construction Ltd — 2024
- Case reference
- 8000863/2024
- Decision date
- 4 September 2024
- Jurisdiction
- Scotland
- Judge
- Employment Judge Sangster Employment
Parties
2 namedClaimant
EMPLOYMENT TRIBUNALS (SCOTLAND) Case No: 8000863/2024 Miss C Potter
Respondent
Key findings
Tribunal's reasoningNo response was presented to the claim, and Employment Judge Sangster issued judgment on the available material under rule 21 of the Employment Tribunal Rules of Procedure 2013. On that basis, the tribunal found that the respondent had made an unauthorised deduction from the claimant’s wages and ordered payment of £1,570.92 gross. It also found that the claimant was dismissed by reason of redundancy and was entitled to a redundancy payment of £1,929.00.
The tribunal further found that the respondent had failed to pay the claimant’s holiday entitlement and ordered payment of £1,099.64 gross. It also found that the claimant was dismissed in breach of contract in respect of notice and awarded damages of £1,570.92. The judgment states that, for the gross sums awarded for wages and holiday pay, the respondent may deduct income tax and employee National Insurance contributions if required by law and if it remits those sums to HMRC and provides written evidence to the claimant.
Claims and outcomes
4 findings recorded| Claim type | Issue or finding | Outcome | Protected characteristic | Award |
|---|---|---|---|---|
| Unlawful deduction from wages | The tribunal found an unauthorised deduction from wages and ordered payment of £1,570.92 gross. | Upheld | — | £1,571 |
| Redundancy | The tribunal found the claimant was dismissed by reason of redundancy and entitled to a redundancy payment of £1,929.00. | Upheld | — | £1,929 |
| Holiday pay | The tribunal found the respondent failed to pay holiday entitlement and ordered £1,099.64 gross. | Upheld | — | £1,100 |
| Breach of contract | The tribunal found dismissal in breach of contract in respect of notice and awarded damages of £1,570.92. | Upheld | — | £1,571 |
Remedy
Monetary award- Total award
- £6,170
- across all upheld claims
Legal tests applied
1 reference- Rule 21 of the Employment Tribunal Rules of Procedure 2013
Official outcome judgment PDF
Gov.uk primary recordThe official judgment PDF on gov.uk contains the tribunal's outcome, reasoning, and any remedy details. Where this page does not yet show extracted outcomes for every claim, use the PDF as the authoritative source.
Published on gov.uk under the Open Government Licence v3.0.
How we got this data
Case essentials (reference, date, judge, venue, country, claim categories) are extracted from the structured metadata gov.uk publishes alongside each decision. Parties and monetary figures are extracted from the judgment PDF text. Key findings and per-claim outcomes require a second extraction pass that is not yet complete for this case — until then, the primary source linked above is the authoritative record. See full methodology.
Named in this case and want it removed? Submit a takedown request. The page will be withdrawn on receipt and the editor will follow up within five working days.